Types of testing under White/Glass Box Testing Strategy:
Unit Testing:
The developer carries out unit testing in order to check if the particular module or unit of code is working fine. The Unit Testing comes at the very basic level as it is carried out as and when the unit of the code is developed or a particular functionality is built.
Static and dynamic Analysis:
Static analysis involves going through the code in order to find out any possible defect in the code. Dynamic analysis involves executing the code and analyzing the output.
Statement Coverage:
In this type of testing the code is executed in such a manner that every statement of the application is executed at least once. It helps in assuring that all the statements execute without any side effect.
Branch Coverage:
No software application can be written in a continuous mode of coding, at some point we need to branch out the code in order to perform a particular functionality. Branch coverage testing helps in validating of all the branches in the code and making sure that no branching leads to abnormal behavior of the application.
Security Testing:
Security Testing is carried out in order to find out how well the system can protect itself from unauthorized access, hacking – cracking, any code damage etc. which deals with the code of application. This type of testing needs sophisticated testing techniques.
Mutation Testing:
A kind of testing in which, the application is tested for the code that was modified after fixing a particular bug/defect. It also helps in finding out which code and which strategy of coding can help in developing the functionality effectively.
Methods of Black Box Testing
2.Equivalence Partitioning
3.Error Guessing
Boundary Value Analysis (BVA) is a test Functional Testing technique where the extreme boundary values are chosen. Boundary values include maximum, minimum, just inside/outside boundaries, typical values, and error values.
Extends equivalence partitioning
Test both sides of each boundary
Look at output boundaries for test cases too
Test min, min-1, max, max+1, typical values
Equivalence Partitioning:
Equivalence partitioning is a black box testing method that divides the input domain of a program into classes of data from which test cases can be derived.
How is this partitioning performed while testing:
1. If an input condition specifies a range, one valid and one two invalid classes are defined.
2. If an input condition requires a specific value, one valid and two invalid equivalence classes are defined.
3. If an input condition specifies a member of a set, one valid and one invalid equivalence class is defined.
4. If an input condition is Boolean, one valid and one invalid class is defined.
Error Guessing:
This is purely based on previous experience and judgment of tester. Error Guessing is the art of guessing where errors can be hidden. For this technique there are no specific tools, writing the test cases that cover all the application paths.
Comparison Testing:
Different independent versions of same software are used to compare to each other for testing in this method.
Graph Based Testing Methods:
Each and every application is build up of some objects. All such objects are identified and graph is prepared. From this object graph each object relationship is identified and test cases written accordingly to discover the errors.
Black Box Testing
Also known as functional testing. Black box testing is a software testing technique whereby the internal workings of the item being tested are not known by the tester. For example, in a black box test on a software design the tester only knows the inputs and what the expected outcomes should be and not how the program arrives at those outputs. The tester does not ever examine the programming code and does not need any further knowledge of the program other than its specifications.
The advantages of this type of testing include:
- The test is unbiased because the designer and the tester are independent of each other.
- The tester does not need knowledge of any specific programming languages.
- The test is done from the point of view of the user, not the designer.
- Test cases can be designed as soon as the specifications are complete.
The disadvantages of this type of testing include:
- The test can be redundant if the software designer has already run a test case.
- The test cases are difficult to design.
- Testing every possible input stream is unrealistic because it would take a inordinate amount of time; therefore, many program paths will go untested.
Types of software Testing
Software Testing Types:
Black box testing - Internal system design is not considered in this type of testing. Tests are based on requirements and functionality.
White box testing - This testing is based on knowledge of the internal logic of an application’s code. Also known as Glass box Testing. Internal software and code working should be known for this type of testing. Tests are based on coverage of code statements, branches, paths, conditions.
Unit testing - Testing of individual software components or modules. Typically done by the programmer and not by testers, as it requires detailed knowledge of the internal program design and code. may require developing test driver modules or test harnesses.
Incremental integration testing - Bottom up approach for testing i.e continuous testing of an application as new functionality is added; Application functionality and modules should be independent enough to test separately. done by programmers or by testers.
Integration testing - Testing of integrated modules to verify combined functionality after integration. Modules are typically code modules, individual applications, client and server applications on a network, etc. This type of testing is especially relevant to client/server and distributed systems.
Functional testing - This type of testing ignores the internal parts and focus on the output is as per requirement or not. Black-box type testing geared to functional requirements of an application.
System testing - Entire system is tested as per the requirements. Black-box type testing that is based on overall requirements specifications, covers all combined parts of a system.
End-to-end testing - Similar to system testing, involves testing of a complete application environment in a situation that mimics real-world use, such as interacting with a database, using network communications, or interacting with other hardware, applications, or systems if appropriate.
Sanity testing - Testing to determine if a new software version is performing well enough to accept it for a major testing effort. If application is crashing for initial use then system is not stable enough for further testing and build or application is assigned to fix.
Regression testing - Testing the application as a whole for the modification in any module or functionality. Difficult to cover all the system in regression testing so typically automation tools are used for these testing types.
Acceptance testing -Normally this type of testing is done to verify if system meets the customer specified requirements. User or customer do this testing to determine whether to accept application.
Load testing - Its a performance testing to check system behavior under load. Testing an application under heavy loads, such as testing of a web site under a range of loads to determine at what point the system’s response time degrades or fails.
Stress testing - System is stressed beyond its specifications to check how and when it fails. Performed under heavy load like putting large number beyond storage capacity, complex database queries, continuous input to system or database load.
Performance testing - Term often used interchangeably with ’stress’ and ‘load’ testing. To check whether system meets performance requirements. Used different performance and load tools to do this.
Usability testing - User-friendliness check. Application flow is tested, Can new user understand the application easily, Proper help documented whenever user stuck at any point. Basically system navigation is checked in this testing.
Install/uninstall testing - Tested for full, partial, or upgrade install/uninstall processes on different operating systems under different hardware, software environment.
Recovery testing - Testing how well a system recovers from crashes, hardware failures, or other catastrophic problems.
Security testing - Can system be penetrated by any hacking way. Testing how well the system protects against unauthorized internal or external access. Checked if system, database is safe from external attacks.
Compatibility testing - Testing how well software performs in a particular hardware/software/operating system/network environment and different combination s of above.
Comparison testing - Comparison of product strengths and weaknesses with previous versions or other similar products.
Alpha testing - In house virtual user environment can be created for this type of testing. Testing is done at the end of development. Still minor design changes may be made as a result of such testing.
Beta testing - Testing typically done by end-users or others. Final testing before releasing application for commercial purpose.
Bug Life Cycle
1) New: When QA files new bug.
2) Deferred: If the bug is not related to current build or can not be fixed in this release or bug is not important to fix immediately then the project manager can set the bug status as deferred.
3) Assigned: ‘Assigned to’ field is set by project lead or manager and assigns bug to developer.
4) Resolved/Fixed: When developer makes necessary code changes and verifies the changes then he/she can make bug status as ‘Fixed’ and the bug is passed to testing team.
5) Could not reproduce: If developer is not able to reproduce the bug by the steps given in bug report by QA then developer can mark the bug as ‘CNR’. QA needs action to check if bug is reproduced and can assign to developer with detailed reproducing steps.
6) Need more information: If developer is not clear about the bug reproduce steps provided by QA to reproduce the bug, then he/she can mark it as “Need more information’. In this case QA needs to add detailed reproducing steps and assign bug back to dev for fix.
7) Reopen: If QA is not satisfy with the fix and if bug is still reproducible even after fix then QA can mark it as ‘Reopen’ so that developer can take appropriate action.
8 ) Closed: If bug is verified by the QA team and if the fix is ok and problem is solved then QA can mark bug as ‘Closed’.
9) Rejected/Invalid: Some times developer or team lead can mark the bug as Rejected or invalid if the system is working according to specifications and bug is just due to some misinterpretation.
Severity and Priority of Bugs
Urgent/Show – stopper: Like system crash or error message forcing to close the window, System stops working totally or partially. A major area of the users system is affected by the incident and It is significant to business processes.
Medium/Workaround: When a problem is required in the specs but tester can go on with testing. It affects a more isolated piece of functionality. It occurs only at one or two customers or is intermittent.
Low: Failures that are unlikely to occur in normal use. Problems do not impact use of the product in any substantive way. Have no or very low impact to business processes
State exact error messages.
PRIORITY means something Deserves Prior Attention. It represents the importance of a bug from Customer point of view. Voices precedence established by urgency and it is associated with scheduling a bug Priority Levels can be defined as follows:
High: This has a major impact on the customer. This must be fixed immediately.
Medium: This has a major impact on the customer. The problem should be fixed before release of the current version in development or a patch must be issued if possible.
Low: This has a minor impact on the customer. The flaw should be fixed if there is time, but it can be deferred until the next release.
Software Testing Key Concepts
* Input Combination and Preconditions: Testing all combination of inputs and initial state (preconditions), is not feasible. This means finding large number of infrequent defects is difficult.
* Static and Dynamic Analysis: Static testing does not require execution of the code for finding defects, whereas in dynamic testing, software code is executed to demonstrate the results of running tests.
* Verification and Validation: Software testing is done considering these two factors.
1. Verification: This verifies whether the product is done according to the specification?
2. Validation: This checks whether the product meets the customer requirement?
* Software Quality Assurance: Software testing is an important part of the software quality assurance. Quality assurance is an activity, which proves the suitability of the product by taking care of the quality of a product and ensuring that the customer requirements are met.
Sunday, March 28, 2010
Test Life Cycle
2. Test Plan
3. Test Design.
4. Design Reviews
5. Code Reviews
6. Test Cases preparation.
7. Test Execution
8. Test Reports.
9. Bugs Reporting
10. Reworking on patches.
11. Release to production.
Requirements Stage
Normally in many companies, developers itself take part in the requirements stage. Especially for product-based companies, a tester should also be involved in this stage. Since a tester thinks from the user side whereas a developer can’t. A separate panel should be formed for each module comprising a developer, a tester and a user. Panel meetings should be scheduled in order to gather everyone’s view. All the requirements should be documented properly for further use and this document is called “Software Requirements Specifications”.
Test Plan
Without a good plan, no work is a success. A successful work always contains a good plan. The testing process of software should also require good plan. Test plan document is the most important document that brings in a process – oriented approach. A test plan document should be prepared after the requirements of the project are confirmed. The test plan document must consist of the following information:
• Total number of features to be tested.
• Testing approaches to be followed.
• The testing methodologies
• Number of man-hours required.
• Resources required for the whole testing process.
• The testing tools that are to be used.
• The test cases, etc
Test Design
Test Design is done based on the requirements of the project. Test has to be designed based on whether manual or automated testing is done. For automation testing, the different paths for testing are to be identified first. An end to end checklist has to be prepared covering all the features of the project.
The test design is represented pictographically. The test design involves various stages. These stages can be summarized as follows:
• The different modules of the software are identified first.
• Next, the paths connecting all the modules are identified.
Then the design is drawn. The test design is the most critical one, which decides the test case preparation. So the test design assesses the quality oftesting process.
Test Cases Preparation
Test cases should be prepared based on the following scenarios:
• Positive scenarios
• Negative scenarios
• Boundary conditions and
• Real World scenarios
Design Reviews
The software design is done in systematical manner or using the UML language. The tester can do the reviews over the design and can suggest the ideas and the modifications needed.
Code Reviews
Code reviews are similar to unit testing. Once the code is ready for release, the tester should be ready to do unit testing for the code. He must be ready with his own unit test cases. Though a developer does the unit testing, a tester must also do it. The developers may oversee some of the minute mistakes in the code, which a tester may find out.
Test Execution and Bugs Reporting
Once the unit testing is completed and the code is released to QA, the functional testing is done. A top-level testing is done at the beginning of the testing to find out the top-level failures. If any top-level failures occur, the bugs should be reported to the developer immediately to get the required workaround.
The test reports should be documented properly and the bugs have to be reported to the developer after the testing is completed.
Once the bugs are fixed, another release is given to the QA with the modified changes. Regression testing is executed. Once the QA assures the software, the software is released to production. Before releasing to production, another round of top-level testing is done.
The testing process is an iterative process. Once the bugs are fixed, the testing has to be done repeatedly. Thus the testing process is an unending process.
What makes a good Software QA engineer?
Verification and Validation
* Verification typically involves reviews and meetings to evaluate documents, plans, code, requirements, and specifications.
* The determination of consistency, correctness & completeness of a program at each stage.
Validation:
* Validation typically involves actual testing and takes place after verifications are completed
* The determination of correctness of a final program with respect to its requirements.
Introduction to Software Testing
* Error: Error or mistake is a human action that produces wrong or incorrect result.
* Defect (Bug, Fault): A flaw in the system or a product that can cause the component to fail or misfunction.
* Failure: It is the variance between the actual and expected result.
* Risk: Risk is a factor that could result in negativity or a chance of loss or damage.
Thus Software testing is the process of finding defects/bugs in the system, that occurs due to an error in the application, which could lead to failure of the resultant product and increase in probability of high risk. In short, software testing have different goals and objectives, which often include:
1. finding defects;
2. gaining confidence in and providing information about the level of quality;
3. preventing defects.
Software Quality Assurance
* Software Quality Assurance involves reviewing and auditing the software products and activities to verify that they comply with the applicable procedures and standards and providing the software project and other appropriate managers with the results of these reviews and audits.